Project News
Part of Richard Gilder Center for Science, Education, and Innovation.
Download the Final Environmental Impact Statement or view all project documents.
7/11/2023
We are pleased to announce that the revitalized sections of Theodore Roosevelt Park next to the Richard Gilder Center for Science, Education, and Innovation are now open to the public.
Please join us on the west side of Theodore Roosevelt Park on Thursday, July 13, for community celebrations of the park reopening:
- 4-6 pm: Join neighbors and elected officials to mark the renovation, which includes new plantings, benches, paths, and gathering areas.
- 7 pm: Join a viewing party for Manhattanhenge—which occurs when the setting Sun lines up with the cross-streets of Manhattan—that will take place in the park, featuring live music by the Williamsburg Salsa Orchestra. Sunset is expected at 8:21 pm.
This event is being held in partnership with Congressman Jerry Nadler, Senator Brad Hoylman-Sigal, Assemblymember Linda B. Rosenthal, Senator Jose M. Serrano, Manhattan Borough President Mark Levine, New York City Council Member Gale Brewer, and Community Board 7.
Both events will be held outdoors and will be cancelled in case of inclement weather. A notice of cancellation will be posted to amnh.org/gilder-news.
5/5/2023
We are pleased to announce that the Gilder Center opened to the public yesterday at 2 pm, along with an additional section of Theodore Roosevelt Park adjacent to the entrance.
Going forward, these updates will shift from a biweekly schedule to periodic updates about key milestones in the renovation of Theodore Roosevelt Park.
Ongoing activities on the Gilder Center are scheduled to include:
- Continued renovation of Theodore Roosevelt Park. Hardscape and planting installation is expected to continue through mid- to late June.
- Reconstruction of the sidewalk, curb, roadway, bike lane, and pedestrian islands. This work is scheduled to begin once the remainder of the park work is complete in mid- to late June.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site.Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
4/14/2023
We are pleased to announce that the Gilder Center is scheduled to open on May 4.
Please note that there is weekend work scheduled for Saturday, April 15. This work will include tree pruning and maintenance throughout the site.
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 3-4 trucks on average arriving per day, including concrete trucks, and flatbed trucks
- Mechanical and electrical work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, bollard installation, and soil placement and plantings
- Fence installation around the 81st Street lawn
- Tree planting throughout the site
- Interior building work may occur on Saturdays and Sundays. The activities will not produce significant noise.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site.Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
3/31/2023
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park
- Fence installation around the 81st Street lawn will begin
- Tree planting throughout the site
- Interior building work may occur on Saturdays and Sundays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
3/17/2023
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park
- Tree planting will begin, requiring minor modifications to the construction fence near the Nobel Monument
- Interior building work may occur on Saturdays and Sundays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
3/3/2023
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park
- Interior building work may occur on Saturdays and Sundays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
2/17/2023
Please note that there is weekend work scheduled for Saturday, February 18, Sunday, February 19, Saturday, February 25, and Sunday, February 26:
- This work will be limited to park work, including soil and paving installation in the park. The work will occur between 9 am and 5 pm, and there will be 2-3 trucks accessing the site.
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park
- Interior building work may occur on Saturdays and Sundays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
2/2/2023
Please note that there is weekend work scheduled for Saturday, February 4, Sunday, February 5, Saturday, February 11, and Sunday, February 12:
- This work will be limited to park work, including soil and paving installation in the park. The work will occur between 9 am and 5 pm, and there will be 2-3 trucks accessing the site.
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Utility connection work along Columbus Avenue. This work will occur from 9 am to 3 pm and includes trenching across Columbus Avenue for the new sewer connection
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park
- Interior building work may occur on Saturdays and Sundays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
1/20/2023
Please note that there is weekend work scheduled for Saturday, January 21, Sunday, January 22, Saturday, January 28, and Sunday, January 29:
- This work will be limited to park work, including soil and paving installation in the park. The work will occur between 9 am and 5 pm, and there will be 2-3 trucks accessing the site.
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Utility connection work along Columbus Avenue. This work will occur from 9 am to 3 pm and includes trenching across Columbus Avenue for the new sewer connection
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays and Sundays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
1/6/2023
Please note that there is weekend work scheduled for Saturday, January 7, Sunday, January 8, and Saturday, January 14:
- This work will be limited to park work, including soil and paving installation in the park. The work will occur between 9 am and 5 pm, and there will be 2-3 trucks accessing the site.
Over the next 2 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Utility connection work along Columbus Avenue. This work will occur from 9 am to 3 pm and includes trenching across Columbus Avenue for the new sewer connection
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
12/15/2022
Please note that there is no work scheduled for Monday, December 26, and Monday, January 2.
Please note that there is weekend work scheduled for Saturday, December 31:
- This work will be limited to insulation and caulking installation, and hand-set stone placement on the west facade of the building. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 10 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Utility connection work along Columbus Avenue. This work will occur from 9 am to 3 pm and includes trenching across Columbus Avenue for the new sewer connection
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
12/1/2022
Please note that there is weekend work scheduled for Saturday, December 3, and Saturday, December 10:
- This work will be limited to insulation and caulking installation, and hand-set stone placement on the west facade of the building. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Utility connection work along Columbus Avenue. This work will occur from 9 am to 3 pm and includes trenching across Columbus Avenue for the new sewer connection
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
11/18/2022
Please note that there will be no work on Thursday, November 24.
Please note that there is weekend work scheduled for Saturday, November 19, and Saturday, November 26:
- This work will be limited to insulation and caulking installation, hand-set stone placement on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Utility connection work along Columbus Avenue is scheduled to begin in the next several weeks. This work will be done during daytime hours and involves trenching across Columbus Avenue for the new sewer connection.
Completed:
- The newly renovated northern section of Theodore Roosevelt Park has reopened.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
11/4/2022
Please note that there is weekend work scheduled for Saturday, November 5, and Saturday, November 12:
- This work will be limited to insulation and caulking installation, and hand-set stone placement on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including stone deliveries, concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Completed:
- Stone panel installation on the west facade of the building has been completed (hand-set stone, caulking, and other facade work is ongoing)
Upcoming:
- Utility connections along Columbus Avenue later this fall
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
10/21/2022
Please note that there is weekend work scheduled for Saturday, October 22, and Saturday, October 29:
- This work will be limited to facade stone, waterproofing and insulation installation on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including stone deliveries, concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Delivery and installation of stone panels for the west facade
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Utility connections along Columbus Avenue later this fall
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
10/7/2022
We are pleased to announce that the Richard Gilder Center for Science, Education, and Innovation will open to the public on February 17, 2023.
The northern part of the newly renovated Theodore Roosevelt Park will open at the end of this month, weather permitting. Park renovations will continue through the spring planting season.
Please note that there is weekend work scheduled for Saturday, October 8, and Saturday, October 15:
- This work will be limited to facade stone, waterproofing and insulation installation on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including stone deliveries, concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Delivery and installation of stone panels for the west facade
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, soil placement and plantings, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Utility connections along Columbus Avenue later this fall
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
9/23/2022
Please note that there is weekend work scheduled for Saturday, September 24, and Saturday, October 1:
- This work will be limited to facade stone, waterproofing and insulation installation on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including stone deliveries, concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Delivery and installation of stone panels for the west facade
- Removal of portions of the sidewalk shed (overhead protection) along Columbus Avenue
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise
Upcoming:
- Utility connections along Columbus Avenue later this fall
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
9/9/2022
Please note that there is weekend work scheduled for Saturday, September 10, and Saturday, September 17:
- This work will be limited to facade stone, waterproofing and insulation installation on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including stone deliveries, concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Delivery and installation of stone panels for the west facade
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Utility connections along Columbus Avenue later this fall
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
8/26/2022
Please note that there is weekend work scheduled for Saturday, August 27:
- This work will be limited to facade stone, waterproofing and insulation installation on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Please note that there is no work scheduled for Monday, September 5, for Labor Day.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including stone deliveries, concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Delivery and installation of stone panels for the west facade
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Utility connections along Columbus Avenue later this fall
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
8/12/2022
Please note that there is weekend work scheduled for Saturday, August 13, and Saturday, August 20:
- This work will be limited to the continuation of waterproofing and insulation installation on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Mobilization of a crane for the facade stone panel installation
- Delivery and installation of stone panels for the west facade
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Park renovation work, including installation of sub-base, concrete and hex pavers for the paths, underground utility work, and renovations of the park at the southern end of the site (adjacent to the Museum’s service drive)
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Utility connections along Columbus Avenue
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
7/29/2022
Please note that there is weekend work scheduled for Saturday, July 30, and Saturday, August 6:
- This work will be limited to the setting and installation of the west facade glass via crane as well as continuation of waterproofing and insulation installation on the west facade of the building, and work on the park renovations. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Delivery and installation of stone panels for the west facade
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including excavating and preparing for sub-base, sub-base concrete and hex paver installation, installation of drains and manholes, and underground utility work
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Utility connections along Columbus Avenue
- Commencing park renovations at the southern end of the site
Completed:
- Installation of the storm water retention tank
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
7/7/2022
Please note that there is weekend work scheduled for Saturday, July 9, and Saturday, July 16:
- This work will be limited to the setting and installation of the west facade glass via crane as well as continuation of waterproofing and insulation installation on the west facade of the building. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including excavating and preparing for sub-base, installation of the storm water retention tank, installation of drains and manholes, and underground utility work
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Delivery and installation of stone panels for the west facade
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
6/23/2022
Please note that there is weekend work scheduled for Saturday, June 25:
- This work will be limited to the setting and installation of the west facade glass via crane as well as continuation of waterproofing and insulation installation on the west facade of the building. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Please note that there is no work scheduled for Monday, July 4.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including excavating and preparing for sub-base, installation of the storm water retention tank, installation of drains and manholes, and underground utility work
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Delivery and installation of stone panels for the west facade
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
6/10/2022
Please note there is weekend work scheduled for Saturday, June 11, and Saturday, June 18:
- This work will be limited to the setting and installation of the west facade glass via crane as well as continuation of waterproofing and insulation installation on the west facade of the building. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Interior building fit-outs, including tile installation, ceiling panel installation, sheet rock installation, and other interior finishes
- Waterproofing installation
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including excavating and preparing for sub-base, installation of drains and manholes, and underground utility work
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Delivery and installation of stone panels for the west facade
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
5/26/2022
Please note that there is no work scheduled for the weekend of May 28 and 29, and there is no work scheduled for Memorial Day, Monday, May 30.
Please note there is weekend work scheduled for Saturday, June 4:
- This work will be limited to boom truck lift operations to deliver materials up to the roof and waterproofing installation on some of the facade. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Stucco and brick facade work on the east facade
- Mechanical and electrical utility work
- Waterproofing installation
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including excavating and preparing for sub-base, installation of drains and manholes, and underground utility work
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Delivery and installation of stone panels for the west facade
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
5/13/2022
Please note that the weekend work scheduled for Saturday, May 7, was postponed due to inclement weather and is now scheduled for Saturday, May 14. Additionally, weekend work is also scheduled for Saturday, May 21:
- This work will be limited to boom truck lift operations to deliver materials up to the roof and waterproofing installation on some of the facade. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including drilling supports of excavation for the storm water retention tank, installation of drains and manholes, and underground utility work
- Interior building work may occur on Saturdays. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that the work scheduled for Saturday, May 7, has been postponed due to forecasted high winds.
It is now scheduled for Saturday, May 14.
Please note that there is weekend work scheduled for Saturday, May 7:
- This work will be limited to boom truck lift operations to deliver materials up to the roof and waterproofing installation on some of the facade. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a boom truck.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including drilling supports of excavation for the storm water retention tank, installation of drains and manholes, and underground utility work
- Interior building work on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is late-night work scheduled for Tuesday, April 19:
- There will be a load-in of materials into the Gilder Center via the Ross Terrace, starting at 6 pm on Tuesday, April 19, until approximately midnight. Work will continue on Wednesday, April 20, during regular hours. The Ross Terrace will be closed to the public during this time. This work will not generate significant noise.
Please note that there is weekend work scheduled for Saturday, April 23:
- This work will be limited to mobile crane operations to lift glass into the building and waterproof some of the facade. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a mobile crane.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Facade and interior glass delivery and crane operations to lift and install
- Park renovation work, including drilling supports of excavation for the storm water retention tank, installation of drains and manholes, and underground utility work
- Interior building work on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, April 9:
- This work will be limited to mobile crane operations lifting waterproofing materials to the roof of the building and waterproofing on some of the facade. The work will occur between 9 am and 5 pm, and there will be 5-6 trucks accessing the site, including a mobile crane.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Park renovation work, including excavation for the storm water retention tank, installation of drains and manholes, and underground utility work
- Interior building work on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
Upcoming:
- Facade glass delivery and crane operations to lift and install
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, March 26:
- This work will be limited to a small mobile crane operation to lift fire shutters into the building, as well as some rebar installation, facade work, waterproofing, and window framing. There will be approximately 75 workers onsite. The work will occur between 9 am and 5 pm, and there will be 3-5 trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Site preparation for park restoration work (including removal of hardscape and topsoil)
- Interior building work on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Completed:
- Removal of the office trailers from the site
Upcoming:
- Facade glass delivery and installation
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, March 12:
- This work will be limited to rebar installation, facade work, waterproofing, and window framing, with approximately 75 workers onsite. The work will occur between 9 am and 5 pm, and there will be no trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Removal of the office trailers from the site
- Mobile crane operations lifting HVAC and mechanical equipment to the roof
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Site preparation for park restoration work (including removal of hardscape and topsoil)
- Interior building work on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Upcoming:
- Facade glass and stone panel delivery and installation
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is no work scheduled for Presidents’ Day, Monday, February 21.
Please note that there is weekend work scheduled for Saturday, February 26:
- This work will be limited to rebar installation, waterproofing, and window framing, with approximately 75 workers onsite. The work will occur between 9 am and 5 pm, and there are no planned trucks accessing the site.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Removal of the office trailers from the site
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Site preparation for park restoration work (including removal of hardscape and topsoil)
- Interior building work on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Upcoming:
- Delivery of and setup of the mobile crane that will be used for the installation of roof equipment, the stone façade, and window glass. Delivery of the crane will occur during regular weekday working hours.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that last Saturday’s planned work has been rescheduled for this Saturday, February 12:
- This work will be limited to rebar and shotcrete installation, with approximately 75 workers onsite, and approximately 5 trucks accessing the site. The work will occur between 9 am and 5 pm.
Please note that there is weekend work scheduled for Saturday, February 5:
- This work will be limited to rebar installation, with approximately 75 workers onsite, and approximately 5 trucks accessing the site. The work will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Removal of the office trailers from the site
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Site preparation for park restoration work (including removal of hardscape and topsoil)
- Interior building work on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise.
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, January 22:
- This work will be limited to rebar installation, with approximately 75 workers onsite, and no trucks accessing the site. The work will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Site preparation for park restoration work (including removal of hardscape and topsoil)
- Interior building work on the Gilder Center will occur on Saturdays between 9 am and 5 pm. This work will be limited to floors that have been enclosed, and the activities will not produce significant noise. There will be no trucks accessing the site.
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, January 8:
- This work will be limited to sprayed structural concrete and rebar installation, with approximately 75 workers onsite and approximately 5 trucks accessing the site. The work will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural concrete installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Site preparation for park restoration work (including removal of hardscape and topsoil)
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Over the next 2 to 3 weeks, activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Sprayed structural installation, including formwork and rebar cage installation
- Mechanical and electrical utility work
- Waterproofing installation
- Window framing
- Site preparation for park restoration work (including removal of hardscape and topsoil)
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, December 18:
- This work will be limited to rebar installation. There will be approximately 75 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
- Site preparation for park restoration work (including removal of hardscape and topsoil)
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, December 4:
- This work will be limited to rebar installation. There will be approximately 75 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
- Site preparation for park restoration work (including removal of hardscape and topsoil)
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Completed:
- Salvaging benches, fencing, and other items in the area of the park under renovation
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, November 20:
- This work will be limited to rebar installation. There will be approximately 75 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Please note that there is no work scheduled for Thanksgiving, Thursday, November 25.
Over the next 2 to 3 weeks, superstructure activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
- Salvaging benches, fencing, and other items in the area of the park under renovation
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Completed:
- Installation of tree protection and protection for the Nobel monument in the area of the park under renovation
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, November 6:
- This work will be limited to rebar installation. There will be approximately 25 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
- Salvaging benches, fencing, and other items in the area of the park under renovation
- Installation of tree protection and protection for the Nobel monument in the area of the park under renovation
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Completed:
- Installation of the site fence around the park section being renovated
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, October 16:
- This work will be limited to rebar installation. There will be approximately 25 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Please also note that the renovation of the northwest corner of Theodore Roosevelt Park is underway:
- Access to the Arthur Ross Terrace has been diverted to the stairs adjacent to the main entrance to the Rose Center.
- Installation of a site fence around the section being renovated has started.
Over the next 2 to 3 weeks, superstructure activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for COVID-19 health and safety measures.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, October 2:
- This work will be limited to rebar installation. There will be approximately 25 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Please also note that the renovation of the northwest corner of Theodore Roosevelt Park is underway:
- Access to the Arthur Ross Terrace has been diverted to the stairs adjacent to the main entrance to the Rose Center.
- Installation of a site fence around the section being renovated has started.
- For more information about the park renovation, please see the September 17 update below.
Over the next 2 to 3 weeks, superstructure activities on the Gilder Center are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, September 18:
- This work will be limited to rebar installation. There will be approximately 25 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Please also note that the renovations of the northwest corner of Theodore Roosevelt Park are scheduled to begin the week of September 20:
- Renovations to the park, which were planned as a part of the Gilder Center project, will include updating paths and landscaping in an approximately 75,000-square-foot portion of the park adjacent to the Gilder Center to provide more public access, seating, and gathering spaces off the path network, and adding new benches and trees.
- Pedestrian access through the park will be maintained, and the Sunday 79th Street Greenmarket on Columbus Avenue will continue without disruption. Access to the Bull Moose Dog Run will not be affected. However, the area south of the entrance and path at 81st street (including the paths leading to the Nobel Monument) will be inaccessible through Spring/Summer 2022.
- Access to the Arthur Ross Terrace will be diverted to the stairs adjacent to the main entrance to the Rose Center.
- Initial activities will focus on extending a temporary egress path adjacent to the Museum campus, followed by installation of a site fence around the section being renovated
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, and flatbed trucks delivering ductwork, piping, wood framing materials, and mechanical equipment
- Rebar, formwork, and cage installation for structural concrete work
- Mechanical and electrical utility work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Upcoming:
Preparatory work for the renovation of the northwest corner of Theodore Roosevelt Park.
- Renovations to the park, which were planned as a part of the Gilder Center project, will include updating paths and landscaping in an approximately 75,000-square-foot portion of the park adjacent to the Gilder Center to provide more public access, seating, and gathering spaces off the path network, and adding new benches and trees
- Pedestrian access through the park will be maintained, and the Sunday 79th Street Greenmarket on Columbus Avenue will continue without disruption
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, August 28.
- This work will be limited to rebar installation. There will be approximately 25 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, as well as oversized flatbed and other large trucks for deliveries of steel
- Rebar, formwork, and cage installation for structural concrete work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, August 14, and Saturday, August 28.
- This work will be limited to rebar installation. There will be approximately 25 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, as well as oversized flatbed and other large trucks for deliveries of steel
- Rebar, formwork, and cage installation for structural concrete work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, July 31.
- This work will be limited to sprayed structural concrete installation. There will be approximately 25 workers onsite, and there will be no trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, as well as oversized flatbed and other large trucks for deliveries of steel
- Rebar, formwork, and cage installation for structural concrete work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Completed:
- Tower crane deinstallation and removal
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that deinstallation and removal of the tower crane is scheduled for Saturday, July 10, and Sunday, July 11:
- Work will occur between the hours of 9 am and 5 pm
- There will be approximately 10-15 trucks entering and exiting the site each day, to remove the tower crane
- There will be approximately 30 workers onsite, including flaggers to safely direct pedestrians when trucks enter and exit the site
- There are no anticipated impacts on parking or vehicular, bicycle, or pedestrian traffic other than intermittent stoppages to allow trucks to safely enter/exit the site
- In the event of inclement weather, this operation will be rescheduled
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, as well as oversized flatbed and other large trucks for deliveries of steel
- Rebar, formwork, and cage installation for structural concrete work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is no work scheduled for Monday, July 5.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, as well as oversized flatbed and other large trucks for deliveries of steel
- Rebar, formwork, and cage installation for structural concrete work
- Sprayed structural concrete installation
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Upcoming:
Please note that deinstallation and removal of the tower crane is scheduled for Saturday, July 10, and Sunday, July 11:
- Work will be limited to the deinstallation and removal of the tower crane, and will occur between the hours of 9 am and 5 pm
- There will be approximately 10-15 trucks entering and exiting the site each day, to remove the tower crane.
- There will be approximately 30 workers on site, including flaggers to safely direct pedestrians when trucks enter and exit the site
- There are no anticipated impacts on parking, vehicular, bicycle, or pedestrian traffic other than intermittent stoppages to allow trucks to safely enter/exit the site
- In the event of inclement weather, this operation will be rescheduled
Completed:
- Structural steel installation
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that work on the Gilder Center that was scheduled for Saturday, May 15, was rescheduled for Saturday, June 19.
- This work will be limited to moving HVAC system equipment into place. There will be approximately 25 workers onsite and approximately 5 trucks accessing the site. This work will not generate significant noise and will occur between the hours of 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 15 trucks on average arriving per day, including concrete trucks, as well as oversized flatbed and other large trucks for deliveries of steel
- Rebar, formwork, and cage installation for structural concrete work
- Sprayed structural concrete testing, and beginning of sprayed concrete installation
- Installation of masonry block walls and steel
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is no work scheduled for Memorial Day, Monday, May 31.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete trucks, as well as oversized flatbed and other large trucks for deliveries of steel
- Rebar, formwork, and cage installation for structural concrete work
- Installation of masonry block walls and steel
- Installation of interior 24/7 temporary construction lighting
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Upcoming:
- Sprayed structural concrete operations
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is weekend work scheduled for Saturday, May 15.
- This work will be limited to moving HVAC system equipment into place. There will be approximately 25 workers onsite, and approximately 5 trucks accessing the site. This work will not generate significant noise, and will occur between the hours of 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete and steel deliveries
- Rebar, formwork, and cage installation for structural concrete work
- Installation of masonry block walls and steel for the northeast portion of the building
- Installation of interior 24/7 temporary construction lighting
- All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Upcoming:
- Sprayed structural concrete operations
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete and steel deliveries
- Rebar, formwork, and cage installation for structural concrete work
- Installation of masonry block walls and steel for the northeast portion of the building
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is work scheduled for Saturday, April 17.
- This work will be limited to backfilling soil between the supports of excavation and foundation of the Gilder Center. There will be approximately 25 workers onsite, and there will be approximately 10 trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the seventh-floor level
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the sixth-floor level
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Work on the Gilder Center resumed after New York City Department of Buildings (DOB) rescinded a stop work order on Wednesday, March 9, after re-inspection.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the fifth-floor level
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Following a routine site visit, the New York City Department of Buildings (DOB) issued a stop work order for the Gilder Center work on Wednesday, February 17, based on issues with a non-structural permanent stair. The contractor has addressed the issues, and we are awaiting DOB’s direction that the order is rescinded.
Over the next 2 to 3 weeks, superstructure activities are scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the fourth- and fifth-floor levels
- Testing and commissioning the hoist (external construction elevator)
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Superstructure is underway, currently working on the fourth floor. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the fourth-floor level
- Installing the hoist (external construction elevator)
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Completed:
- Roof protection for adjacent buildings
- Superstructure for the cellar and first through third floors
Please note that there is work is scheduled for Saturday, February 6.
- This work will be limited to lifting materials into place to install the hoist (construction elevator) and installing adjacent building roof protection (rescheduled from weekday early morning hours). Installation of the hoist is required by the New York City Fire Department. There will be approximately 20 to 30 workers onsite, and there may be a limited number of trucks accessing the site. The work will not generate significant noise and will occur between 9 am and 5 pm.
Superstructure work is underway, currently working on the third and fourth floors. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the third- and fourth-floor levels
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that there is additional work scheduled for the next two weeks:
- Work is scheduled for Saturday, January 23, between 9 am and 5 pm: this work will be limited to rebar, formwork, and mechanical/electrical work. There will be approximately 20 to 30 workers onsite, and there may also be a limited number of trucks accessing the site.
- Early morning work during weekdays, planned to begin the week of January 25, starting as early as 6 am, due to safety considerations: this work will be limited to lifting roof protection materials onto adjacent buildings and will not generate significant noise.
Superstructure work is underway, currently working on the second and third floors. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the second- and third-floor levels
- Installation of scaffolding and building protection for adjacent buildings
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Superstructure work is underway, currently working on the second floor. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the second-floor level
- Installation of scaffolding and building protection for adjacent buildings
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Completed:
- Superstructure for the cellar and first floor
accordion
Please note that there is no work scheduled for Friday, December 25, and Friday, January 1.
Superstructure work is underway, currently working on the cellar and first-floor levels. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams, and slab at the first-floor level
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Upcoming:
- Installation of scaffolding and building protection for adjacent buildings
Please note that there is no work scheduled for Friday, December 25, and Friday, January 1.
Superstructure work is underway, currently working on the cellar and first-floor levels. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the worksite, with about 30 trucks on average arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams at the cellar level and first-floor slab
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Upcoming:
- Installation of scaffolding and building protection for adjacent buildings
Please note that there is no work scheduled for Thanksgiving, Thursday, November 26.
Superstructure work is underway, currently working on the cellar level. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 20-30 trucks arriving per day, including concrete deliveries
- Rebar and formwork installation
- Pouring concrete walls and beams at the cellar level and first-floor slab
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Completed:
- Excavation and foundation operations for the Gilder Center have been completed.
Please note that work on the Gilder Center is scheduled for Saturday, November 14 (rescheduled from Saturday, November 7):
- Work will be limited to finishing foundation work in critical areas, and will occur between the hours of 9 am and 5 pm
- There will be approximately 30 workers on site, and there may also be limited truck activity accessing the site
Superstructure work has begun. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 20-30 trucks arriving per day, including concrete deliveries
- Finishing the pouring of concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Constructing the concrete pumping enclosure
- Intermittent soil and rock removal
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that work on the Gilder Center is scheduled for Saturday, November 7:
- Work will be limited to finishing foundation work in critical areas, and will occur between the hours of 9 am and 5 pm
- There will be approximately 30 workers on site, and some limited concrete trucks may access the site
- In the event of inclement weather, this operation will be rescheduled for November 14
Please also note that an overnight fire system test of Building 17 (the brick building north of the Gilder Center site) is scheduled for Monday, November 2, to Tuesday, November 3:
- The test will take place entirely within the building, and no significant noise is anticipated. To facilitate the testing, a truck will be parked in Theodore Roosevelt Park near the steps to the Ross Terrace.
Excavation and foundation work on the Gilder Center will be completed shortly, and work is transitioning into the superstructure phase. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 20-30 trucks arriving per day, including concrete deliveries
- Finishing the pouring of concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Testing and commissioning of the tower crane
- Constructing the concrete pumping enclosure
- Intermittent soil and rock removal
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Please note that delivery of a tower crane is scheduled for Saturday, October 17, and Sunday, October 18:
- Work will be limited to the delivery of a tower crane, and will occur between the hours of 6 am and 9 pm on both Saturday and Sunday
- There will be approximately 10-15 trucks entering and exiting the site each day to deliver the tower crane, deliver and remove a second, smaller crane that will be used to assemble the tower crane, and other materials
- There will be approximately 30 workers on site, including flaggers to safely direct pedestrians when trucks enter and exit the site
- The crane will be delivered via Columbus Avenue, and there are no anticipated impacts on parking, vehicular, bicycle, or pedestrian traffic other than intermittent stoppages to allow trucks to safely enter/exit the site
- In the event of inclement weather, this operation will be rescheduled
Excavation and foundation work on the Gilder Center is anticipated to be completed by the end of October. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including concrete deliveries
- Pouring concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Underpinning and foundation installation using demo hammers, jack hammers, and other hand tools
- Intermittent soil and rock removal
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Completion of excavation and foundation phase of work
- Beginning the superstructure phase of work, including rebar and formwork deliveries and construction of the concrete pump station
Please note that work on the Gilder Center is scheduled for Saturday, October 3.
- Work will be limited to activities necessary to prepare the site for the delivery of a tower crane, including waterproofing and rebar work. There are no planned deliveries of equipment or materials. Work will occur between the hours of 9 am and 5 pm.
Excavation and foundation work on the Gilder Center continues. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including concrete deliveries
- Pouring concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Underpinning and foundation installation using demo hammers, jack hammers, and other hand tools
- Intermittent soil and rock removal
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- The delivery of a tower crane is anticipated to occur during one Saturday in October.
Excavation and foundation work on the Gilder Center continues. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including concrete deliveries
- Pouring concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Underpinning and foundation installation using demo hammers, jack hammers, and other hand tools
- Intermittent soil and rock removal
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
The Museum is preparing to open on September 9 for the general public. More information can be found at amnh.org/health-safety.
On Saturday, September 5, there will be approximately 8-10 workers onsite rolling out waterproofing material onto the slab-on-grade to prepare for concrete pours the following week. No trucks and no mechanical equipment will be used.
Please note there is no work scheduled for Labor Day, Monday, September 7.
Excavation and foundation work on the Gilder Center continues. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including concrete deliveries
- Pouring concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Underpinning and foundation installation using demo hammers, jack hammers, and other hand tools
- Intermittent soil and rock removal
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
The Museum is preparing to open on September 2 for Members and on September 9 for the general public. More information can be found at amnh.org/health-safety.
Excavation and foundation work on the Gilder Center continues. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including concrete deliveries
- Pouring concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Underpinning and foundation installation using demo hammers, jack hammers, and other hand tools
- Intermittent soil and rock removal
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and hand-washing stations, and social distancing practices where feasible.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
We hope that everyone is healthy and well as COVID-19 continues to impact New York City.
Excavation and foundation work on the Gilder Center continues. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including concrete deliveries
- Pouring concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Underpinning and foundation installation using demo hammers, jack hammers, and other hand tools
- Intermittent soil and rock removal (including rock breaking, where needed)
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
The Museum is preparing to open on September 2 for Members and invited guests, and on September 9 for the general public, pending approval from New York State and New York City for indoor museums to open. Status updates can be found at amnh.org/health-safety
Completed:
- Caisson installation and drilling operations for the foundation of the Gilder Center have been completed
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
We hope that everyone is healthy and well as COVID-19 continues to impact New York City.
Excavation and foundation work on the Gilder Center continues. Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including concrete deliveries
- Pouring concrete for the slab-on-grade
- Below-grade plumbing and electrical infrastructure installation
- Underpinning, caisson, and foundation installation using demo hammers, jack hammers, drills, and other hand tools
- Intermittent soil and rock removal (including rock breaking, where needed)
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and hand washing stations, and social distancing practices where feasible.
The Museum continues to be temporarily closed to the public. Status updates can be found at amnh.org/health-safety.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until approximately 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
We hope that everyone is healthy and well as COVID-19 continues to impact New York City.
Construction on the Gilder Center project has resumed, in accordance with guidelines from the City and State. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Excavation and foundation work continues, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and foundation installation using demo hammers, jack hammers, drills, and other hand tools
- Below-grade plumbing and electrical infrastructure installation
- Pouring concrete for the slab-on-grade foundation
- Intermittent soil and rock removal (including rock breaking, where needed)
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols.
The Museum continues to be temporarily closed to the public. Status updates can be found at amnh.org/health-safety.
Work will occur on weekdays from approximately 7 am to 3:30 pm, but may extend until 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
We hope that everyone is healthy and well as COVID-19 continues to impact New York City.
Construction on the Gilder Center project has resumed, in accordance with guidelines from the City and State. COVID-19 health and safety measures are in place, including medical screenings for all workers entering the site, additional sanitizing and handwashing stations, and social distancing practices where feasible.
Excavation and foundation work continues, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and foundation installation using demo hammers, jack hammers, drills, and other hand tools
- Below grade plumbing and electrical infrastructure installation
- Pouring concrete for the slab-on-grade foundation
- Intermittent soil and rock removal (including rock breaking, where needed)
All activities are conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols.
The Museum continues to be temporarily closed to the public. Status updates can be found at amnh.org/health-safety.
We hope that everyone is healthy and well as COVID-19 continues to impact New York City.
In accordance with guidance from Governor Andrew Cuomo, on Monday, June 8, New York City entered Phase I of reopening under New York Forward, which includes the construction industry.
Construction on the Gilder Center project is expected to resume next week. Prior to construction activities resuming, remobilizing activities to prepare the site began this week. Remobilization activities include:
- Installing a medical screening trailer for all workers who enter the site
- Adding sanitizing and handwashing station
- Preparing the site for construction to resume
Excavation and foundation work will resume the week of June 15, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and foundation installation using demo hammers, jack hammers, drills, and other hand tools
- Below grade plumbing and electrical infrastructure installation
- Soil and rock removal (including rock breaking, where needed)
All activities will be conducted based on New York State reopening guidelines for mandated physical distancing, protective equipment, and cleaning and hygiene protocols.
The Museum continues to be temporarily closed to the public. Status updates can be found at amnh.org/health-safety.
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
We hope that everyone is healthy and well as COVID-19 continues to impact New York City.
We wanted to update you that, following New York State Governor Andrew Cuomo's Executive Order "Continuing Temporary Suspension and Modification of Laws Relating to the Disaster Emergency" (No. 202.13), which directed all non-essential construction to halt, and additional guidance from the Empire State Development Corporation, construction of the Gilder Center will be paused at close of business today, April 3, until further notice.
Crews have been working to secure the site and make it safe in accordance with requirements from the New York City Department of Buildings, and staff will be monitoring the worksite to secure the site and ensure continued safe conditions until work can resume. We will continue to update you as the situation changes.
The Museum continues to be temporarily closed to the public. Status updates and online resources can be found at amnh.org/health-safety.
We hope everyone is healthy and safe as COVID-19 continues to affect New York City. Per Governor Andrew Cuomo’s guidance on essential services under the “New York State on PAUSE” Executive Order, we have noted that construction, which employs essential trades, can safely continue.
- The construction team has implemented enhanced cleaning and hygiene protocols, including disinfecting all surfaces in direct human contact.
- The Museum temporarily closed to the public on March 13 to maintain health and safety during the COVID-19 pandemic. More information, including links to online programs and online access, is available at amnh.org/health-safety.
Please note, work is scheduled for Saturday, March 28, and Saturday, April 4.
- Weekend work will be limited to the installation of pre-delivered materials, which will include only construction activities with minimal noise impact. There will be no deliveries of equipment or materials to the worksite and no trucks entering or exiting the site. Work will occur between the hours of 9 am to 5 pm.
Over the next 2 to 3 weeks, weekday work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and foundation installation using demo hammers, jack hammers, drills, and other hand tools
- Below grade plumbing and electrical infrastructure installation
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Concrete truck deliveries for footing installations
- Slab on-grade installation
Please note that work on the Gilder Center is scheduled for several Saturdays in March, weather permitting.
- Work will be limited to installation of pre-delivered materials, which will include only construction activities with minimal noise impact. There will be no deliveries of equipment or materials to the work site and no trucks entering or exiting the site. Work will occur between the hours of 9 am to 5 pm.
Over the next 2 to 3 weeks, weekday work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and support of excavation installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Concrete truck deliveries for footing installations
*Please note that work on the Gilder Center is scheduled for several Saturdays in March, weather permitting.
- Work will be limited to installation of pre-delivered materials, which will include only construction activities with minimal noise impact. There will be no deliveries of equipment or materials to the work site and no trucks entering or exiting the site. Work will occur between the hours of 9 am to 5 pm.
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and support of excavation installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Continued support of excavation installation, including excavation and sheeting and tie back installation
- Concrete truck deliveries for footing installation
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and support of excavation installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Continued support of excavation installation, including excavation and sheeting and tie back installation
- Concrete truck deliveries for footing installations
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning, caisson, and support of excavation installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Continued support of excavation installation, including excavation and sheeting and tie back installation
- Concrete truck deliveries for footing installations
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning and support of excavation installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Continued support of excavation installation, including excavation and sheeting and tie back installation
- Concrete truck deliveries for footing installations
Community Notice:
Below is information on neighborhood activities unrelated to the Gilder Center project:
- The crane operation to replace chilled water equipment in the Museum complex is underway and is scheduled to be completed by the end of this week. These chillers will aid in the Museum’s energy efficiency efforts. The crane operation is using the Gilder Center construction site to access an area of the Museum and work is occurring during normal weekday work hours.
*Please note that there is no work scheduled for Wednesday, January 1*
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning and support of excavation installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Continued support of excavation installation, including excavation and sheeting and tie back installation
- Concrete truck deliveries for footing installations
Community Notice:
Below is information on neighborhood activities unrelated to the Gilder Center project:
- A crane operation to replace chilled water equipment in the Museum complex is scheduled for the week of January 13-17. These chillers will aid in the Museum’s energy efficiency efforts. The crane operation will use the Gilder Center construction site to access an area of the Museum and will occur during normal weekday work hours. This work is not expected to generate excessive noise.
*Please note that there is no work scheduled for Wednesday, December 25, or Wednesday, January 1*
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day, including some concrete deliveries
- Underpinning and support of excavation installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming up:
- Continued underpinning and caisson installation
- Continued support of excavation installation, including excavation and sheeting and tie back installation
- Concrete truck deliveries for footing installations
Completed:
- Pile drilling for the support of excavation
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day
- Underpinning and caisson (drilled steel and concrete foundation pier) installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Continued support of excavation installation, including pile drilling and sheeting and tie back installation
- Concrete truck deliveries for footing installations
* Please note that there is no work scheduled for Thursday, November 28. Work is scheduled for Wednesday, November 27, but there will be no vehicles accessing the site that day.*
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day
- Underpinning and caisson (drilled steel and concrete foundation pier) installation using demo hammers, jack hammers, drills, and other hand tools
- Soil and rock removal (including rock breaking, where needed)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Continued installation of piles and sheeting to support excavation
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Delivery of equipment and materials to the work site, with about 10-20 trucks arriving per day
- Underpinning and caisson (drilled steel and concrete foundation pier) installation using demo hammers, jack hammers, drills, and other hand tools
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. For excavation and foundation activities, when required, work using noise-emitting machinery will not begin prior to 8 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued underpinning and caisson installation
- Installation of piles and sheeting to support excavation
- Soil and rock removal (including rock breaking, where needed)
Completed:
- Building removals have been completed
Over the next 2 to 3 weeks, work is scheduled to include:
Excavation and foundation work, with associated noise, including:
- Mobilization for excavation and foundation work, including bringing additional machinery on site, with about 10-20 trucks arriving per day
- Underpinning and caisson (drilled steel and concrete foundation pier) installation using demo hammers, jack hammers, drills, and other hand tools
Continued building removals work, including:
- Concrete slab removals of building 16 using demo hammers, jack hammers, and other hand tools
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. When required, work using noise-emitting machinery will not begin prior to 7:30 am. Night or weekend work may occasionally be required for certain construction activities, in which case advance notice will be provided.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
Excavation and foundation work, including:
- Continued underpinning and foundation pier installation
- Installation of piles and sheeting to support excavation
- Soil and rock removal (including rock breaking, where needed)
Over the next 2 to 3 weeks, work is scheduled to include:
- Concrete slab removals of building 16
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Mobilization for excavation and foundation work, including bringing additional machinery on site
Tools and machinery in use include demolition hammers as well as jack hammers and other hand tools.
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. When required, work using noise-emitting machinery will not begin prior to 7:30 am. Night or weekend work may occasionally be required for certain construction activities.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
Excavation and foundation work, with associated noise, including:
- Additional truck trips to the site and delivery of additional machinery
- Underpinning and caisson installation
- Installation of piles and sheeting to support excavation
- Soil and rock removal
Completed:
- The roof slab of building 16 has been removed
Please note that work on the Gilder Center is scheduled for Saturday, September 28, and Saturday, October 5
- Work will be limited to machine and hand tool removal operations for building 16 (the former glass pavilion), with no delivery of equipment or materials to the work site expected and no use of trucks planned. Work will occur between the hours of 9 am to 5 pm.
Over the next 2 to 3 weeks, work is scheduled to include:
- Concrete slab removals of building 16
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Mobilization for excavation and foundation work, including bringing additional machinery on site
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. When required, work using noise-emitting machinery will not begin prior to 7:30 am. Night or weekend work may occasionally be required for certain construction activities.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Underpinning and caisson installation
- Installation of piles and sheeting to support excavation, with associated noise
- Soil and rock removal
Completed:
- Buildings 15 & 15A removals have been completed
Please note that work on the Gilder Center will be occurring on Saturday, September 21, and Saturday, September 28.
- Work will be limited to machine and hand tool removal operations for building 16 (the former glass pavilion), with no delivery of equipment or materials to the work site expected and no use of trucks planned. Work will occur between the hours of 9 am to 5 pm.
Over the next 2 to 3 weeks, work is scheduled to include:
- Concrete slab removals of building 16, working from the roof slab down
- Removal of buildings 15 & 15A
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Mobilization for excavation and foundation work, including bringing additional machinery on site
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. When required, work using noise-emitting machinery will not begin prior to 7:30 am. Night or weekend work may occasionally be required for certain construction activities.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Excavation and foundation work, including additional truck trips to the site and delivery of additional machinery
- Installation of piles and sheeting to support excavation, with associated noise
- Soil and rock removal
Please note that no work is scheduled for Labor Day, Monday, September 2.
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Removal of the structure of the glass pavilion
- Removal of two adjacent buildings (buildings 15 and 15A)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. When required, work using noise-emitting machinery will not begin work prior to 7:30 am. Night or weekend work may occasionally be required for certain construction activities.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Excavation and foundation work
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Removal of the structure of the glass pavilion
- Removal of two adjacent buildings (buildings 15 and 15A)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. When required, work using noise-emitting machinery will not begin prior to 7:30 am. Night or weekend work may occasionally be required for certain construction activities.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued building removals
- Excavation and foundation work
Completed:
- The top level of building 15 has been removed
- The roof of building 16 has been removed
Please note that work on the Gilder Center that was originally scheduled for Saturday, July 20, was rescheduled due to the heat advisory and will take place on Saturday, August 3.
- Due to the heat advisory, work scheduled for Saturday, July 20 has been rescheduled for Saturday, August 3. Work will include only construction activities with minimal impact. It will be limited to machine and hand tool removal operations for buildings 15 and 15A, with no delivery of equipment or materials to the work site expected and no use of trucks planned. Work will occur between the hours of 9 am to 5 pm.
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Removal of the structure of the glass pavilion
- Removal of two adjacent buildings (buildings 15 and 15A)
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 6 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. When required, work using noise-emitting machinery will not begin prior to 7:30 am. Night or weekend work may occasionally be required for certain construction activities.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued building removals
- Excavation and foundation work
Completed:
- The glass and steel has been removed from building 16 (the glass pavilion)
- Construction trailers have been delivered and placed on the work site
- Benches that were formerly located inside the site fence have been moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks
Community Notice:
Below is information on neighborhood activities unrelated to the Gilder Center project:
- NYC Parks began work on the Bull Moose Dog Run, with more information available on the NYC Parks website here
The work scheduled for Saturday, July 20, will be rescheduled due to the heat advisory.
Please note that work on the Gilder Center is scheduled for Saturday, July 20, and Saturday, July 27.
- Work on Saturday, July 20, and Saturday, July 27, will include only construction activities with minimal impact. It will be limited to machine and hand tool removal operations for buildings 15 and 15A, with no delivery of equipment or materials to the work site expected and no use of trucks planned. Work will occur between the hours of 9 am to 5 pm.
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Removal of the structure of the glass pavilion, starting with the roof and working down to the base of the building
- Removal of two adjacent buildings (buildings 15 and 15A)
- Construction trailer delivery and placement on the work site
Unless otherwise noted, work will occur on weekdays from approximately 7 am to 5 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Night or weekend work may occasionally be required for certain construction activities. When required, work using noise-emitting machinery will not begin work prior to 7:30 am.
The work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued building removals
Completed:
- The roof of building 15 has been removed
- The steel framing in the glass pavilion has been removed
- Benches that were formerly located inside the site fence have been moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks
Community Notice:
Below is information on neighborhood activities unrelated to the Gilder Center project:
- The fountains on the Arthur Ross Terrace are temporarily closed while undergoing maintenance, but are expected to open later this week
- NYC Parks will begin work on the Bull Moose Dog Run this month, with more information available on the NYC Parks website here
Please note that there is no work scheduled for Thursday, July 4.
Planned activities are a continuation of the work that has been taking place over the last two weeks as identified in prior updates.
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 5-10 trucks arriving per day
- Removal of the structure of the glass pavilion, starting with the roof and working down to the base of the building
- Removal of two adjacent buildings (buildings 15 and 15A)
- Benches that were formerly located inside the site fence will be moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks
Unless otherwise noted, work activities will occur on weekdays from approximately 7 am to 3:30 pm, with associated construction noise. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Noise-emitting machinery will not begin work prior to 7:30 am.
Work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming up:
- Continued building removals
- Construction trailers will be placed on the work site
Completed:
- All shoring that was needed to support the building removals has been installed
Planned activities are a continuation of the work that has been taking place over the last two weeks as identified in prior updates.
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 4-8 trucks arriving per day
- Installing shoring within the existing buildings and museum structure to support the buildings during their removal
- Removal of the structure of the glass pavilion, starting with the roof and working down to the base of the building, with associated construction noise
- Removal of two adjacent buildings (buildings 15 and 15A)
Unless otherwise noted, work activities will occur on weekdays from approximately 7 am to 3:30 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Some construction noise is anticipated. Noise-emitting machinery will not begin work prior to 7:30 am.
Work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued building removals
- Over the next month, benches that were formerly inside the site fence will be moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks
- Construction trailers will be placed on the work site
June Activities:
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 4-8 trucks arriving per day
- Installing shoring within the existing buildings and museum structure to support the buildings during their removal
- Removal of the structure of the glass pavilion, starting with the roof and working down to the base of the building, with associated construction noise
- Removal of two adjacent buildings (buildings 15 and 15A)
Unless otherwise noted, work activities will occur on weekdays from approximately 7 am to 3:30 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Some construction noise is anticipated. Noise-emitting machinery will not begin work prior to 7:30 am.
Work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Continued building removals
- Over the next month, benches that were formerly inside the site fence will be moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks
- Construction trailers will be placed on the work site
May Activities:
Please note that no work is scheduled for Memorial Day (Monday, May 27).
Over the next 2 to 3 weeks, work is scheduled to include:
- Delivery of equipment and materials to the work site, with about 2 to 3 trucks arriving per day
- Removal of the structure of the glass pavilion
- Continued maintenance and care of the trees protected within the site (including irrigation installation)
- Removal of two adjacent buildings
Unless otherwise noted, work activities will occur on weekdays from approximately 7 am to 3:30 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Some construction noise is anticipated. Noise-emitting machinery will not begin work prior to 7:30 am.
Work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Over the next month, benches that were formerly inside the site fence will be moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks
- Construction trailers will be placed on the work site
Completed:
- The glass panels have been removed from the glass pavilion
- Scaffolding has been installed within the Museum complex to protect the historic façade of the adjacent Museum buildings
- A traffic light that was within the site fence was successfully relocated to a temporary position, outside the fence along the temporary pedestrian and bicycle path, in close coordination with NYC DOT and NYPD.
May Activities:
Over the next 2 to 3 weeks, work is scheduled to include the start of mobilization for the removal of three buildings:
- Delivery of equipment and materials to the work site, with about 2 to 3 trucks arriving per day
- Scaffolding installation to protect the historic façade of adjacent Museum building
- Removal of the glass panels from the glass pavilion
- Removal of the structure of the glass pavilion
- Removal of two adjacent buildings
Unless otherwise noted, work activities will occur on weekdays from approximately 7 am to 3:30 pm. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Some construction noise is anticipated. Noise-emitting machinery will not begin work prior to 7:30 am.
Work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming Up:
- Over the next month, benches that were formerly inside the site fence will be moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks.
- Construction trailers will be placed on the work site.
Completed:
- Bartlett Tree Experts in coordination with NYC Parks planted three trees in Theodore Roosevelt Park to replace three trees that did not survive transplantation.
With this update we are introducing a biweekly update about the Gilder Center Project, providing information about upcoming work and other activities in an at-a-glance format.
There will be an increase in activity on the site this month, including in the number of trucks arriving to deliver materials and equipment, to about 2 to 3 trucks per day. Flaggers will be present to ensure safe and efficient movement of vehicles into and out of the site. Some construction noise is also anticipated.
Over the next 2 to 3 weeks, scheduled work includes:
- Delivery of equipment and materials to the work site
- Roof protection for the surrounding Museum building
- Removal of the structure of the glass pavilion
- Scaffolding installation to protect the historic façade of adjacent Museum building
Unless otherwise noted, work activities will occur on weekdays from approximately 7 am to 3:30 pm. Work activities above are outlined based on the best available information for the current schedule and may be subject to change due to weather or other circumstances.
Coming up:
- Over the next month, Bartlett Tree Experts in coordination with NYC Parks will be planting three trees in Theodore Roosevelt Park to replace three trees that did not survive transplantation.
- Over the next month, benches that were formerly inside the site fence will be moved to other locations around Theodore Roosevelt Park, per the plan developed by NYC Parks.
- Construction trailers will be placed on the work site.
Community Notice:
Below is information on neighborhood activities unrelated to the Gilder Center project:
- In early April, NYC Parks and Friends of Roosevelt Park, working with Emerald Tree Care, identified four trees in the Park as structurally unsound due to rot and removed one of the trees. The paths that had been closed to permit this work, including the path at 80th Street and the stairs to the Museum’s Ross Terrace, have reopened. More information can be found on the Friends of Roosevelt Park website.
Today, the New York State Supreme Court Appellate Division dismissed the challenge to the American Museum of Natural History’s Gilder Center for Science, Education, and Innovation project and unanimously affirmed the lower court ruling in the Museum’s favor in December.
The Gilder Center is a 230,000-square foot project that will significantly enhance the Museum’s science, education, and exhibition spaces and improve visitor experience with an architectural design by Jeanne Gang of Studio Gang. The Gilder Center will be a major new resource for science education for all New Yorkers and visitors from around the world, and we are extremely pleased that we can now turn our attention to proceeding with the project.
The Gilder Center project will also make vital connections among the Museum’s buildings and include a redesign of the adjacent part of Theodore Roosevelt Park.
Since the last update, removal of interior building components of the Weston building and the two adjacent buildings that formerly housed the Museum’s Ichthyology Department has continued. Next steps include selective removal of the glass exterior and roof of the Weston building, with a resulting increase in the number of workers and trucks onsite.
The Museum continues to work to minimize disruption throughout the construction project, and Zac Campbell remains the main contact for Gilder Center construction-related questions or concerns from the neighborhood. He can be reached at 212-769-5243.
We also wanted to pass along information unrelated to the Gilder Center, concerning work that you may see in Theodore Roosevelt Park over the next few days. Friends of Theodore Roosevelt Park has informed the Museum that, working with NYC Parks and Emerald Tree Care, they conducted an assessment and found that four trees in the Park are structurally unsound due to rot. This past weekend, NYC Parks closed a portion of the path near the Nobel Monument due to potential risks to public safety and determined that the four affected trees need to be removed in the coming weeks. More information can be found on the Friends of Theodore Roosevelt Park website here.
Yesterday, a panel of appellate judges issued a decision that allows all work on the Gilder Center to move forward while an appeal of New York State Supreme Court’s decision to dismiss a lawsuit challenging the project proceeds in appellate court.
As work resumes, vehicles will be entering the construction site from Columbus Avenue to facilitate delivery of materials and other site preparation activities. Work will include ground protection and clearing lamp posts, fencing, and other materials in the work area; tree protection for trees that will remain for the duration of the project and tree removal; and top soil removal.
Some of this work will create low-level construction noise. The Museum will be working to minimize disruption throughout the construction project, and Zac Campbell remains the main contact for Gilder Center construction-related questions or concerns from the neighborhood. He can be reached at 212-769-5243.
On December 17, the group opposing the Gilder Center project filed a notice of appeal of the New York State Supreme Court’s decision dismissing their lawsuit. On December 18, they sought an interim stay and a stay pending appeal. An appellate judge issued an interim stay, preventing the Museum from proceeding with certain exterior work until the full panel of appellate judges determines whether to issue a stay pending appeal. The panel will review the motion for a stay pending appeal on an expedited basis, and that decision could be issued later this month.
Beginning next week, the Museum will resume preparations of the construction site for the Gilder Center project.
Vehicles will be entering the site from Columbus Avenue to facilitate delivery of materials and other site preparation activities, including adding ground protection and clearing lamp posts, fencing, and other materials in the work area, which will continue through mid-January. Pruning of the roots of several trees that will remain for the duration of the project will begin early next week as part of the approved tree protection plan and in accordance with New York City Department of Parks and Recreation guidelines.
In addition, work will begin on the seven trees that will be removed, followed by top soil removal, and there also will be work on the exterior of the building to the south of the construction site. This work will create low-level construction noise. Six new canopy trees and 16 new understory trees will be planted after construction is completed as part of the landscape plan for the western portion of the Park.
The Museum is working to minimize disruption throughout the construction project. Zac Campbell remains the main contact for Gilder Center construction-related questions or concerns from the neighborhood. He can be reached at 212-769-5243.
Following a decision by Judge Lynn R. Kotler on Monday, December 10, the Museum will move forward with the Gilder Center project. Judge Kotler dismissed the lawsuit and affirmed that the Museum followed all appropriate procedures in preparation for the Gilder Center project. The expansion will significantly enhance Museum education programs, visitors’ experiences, and scientific work.
We are very excited about moving forward and bringing this important project to fruition, and we will be updating you soon about upcoming work. The Museum will work closely with our partners to minimize any disruption throughout the construction project. In the meantime, Zac Campbell remains the main contact for any Gilder Center construction-related questions or concerns from the neighborhood. He can be reached at 212-769-5243.
As you may know, the American Museum of Natural History was created 150 years ago by New Yorkers who believed that this City needed a great museum to advance scientific research and to serve as a center of learning for school children and visitors. Those goals are still at the heart of our mission—and are even more crucial today.
I’m Michael Novacek, Senior Vice President and Provost of Science at the Museum, and I oversee the Museum’s scientific research and exhibitions. I am reaching out to you today to share the tremendous progress that we are making on the Gilder Center for Science, Education, and Innovation, the new building planned for the west side of our campus, and to share more about why this project is such an important part of the Museum’s service to New York and beyond:
- Modern educational facilities for hundreds of thousands of school children: The Gilder Center’s 13 new or renovated classrooms will offer the latest technology and scientific instrumentation for students and teachers throughout the five boroughs.
- Programming for thousands of New York State teachers: The Gilder Center will support the Museum’s Master of Arts in Teaching program, which educates one-third of all newly-certified New York State teachers in Earth science, and thousands of local science teachers will use the new halls and classrooms for professional development and student learning programs.
- Exhibition halls for visitors and school groups: A new state-of-the-art theater exploring new worlds of scientific discovery, as well as galleries that highlight vital scientific topics—such as insects’ role in our food supply, in human health, and as indicators of climate change—will bring important new science to the public.
- A view into the scientific collections for the public: The Collections Core will hold millions of specimens from the Museum’s research collections — which form an irreplaceable record of life on Earth — in new, state-of the art facilities, to offer visitors a close look at the essential factual evidence that underpins scientific research by scientists and scholars at the Museum and from around the world.
You may have heard about a lawsuit challenging the project. I’d like to correct mischaracterizations that have been raised with some important facts:
- The Museum is passionate about Theodore Roosevelt Park and is committed to improving it. The Museum has worked with Friends of Theodore Roosevelt Park since 2002 to support the Park and recently announced a commitment of $100,000 annually for the next 10 years for the Park’s maintenance. Together with the New York City Department of Parks & Recreation (NYC Parks) and Park Working Group, the Museum developed new designs with more benches and more green space for passive recreational uses. The Parks Department found that these improvements would enhance the adjacent area of the Park by increasing the amount of publicly accessible open space and by providing additional seating and gathering areas.
- At every turn, the Museum has worked to minimize the impact on the Park. To reduce the project’s overall footprint, the Museum revised the project’s plans to keep the extension of its footprint to only .25 acre beyond what it is today in the 17.58-acre park. While seven trees will be removed following appropriate court resolution, 22 new trees (including six canopy trees) will be planted once construction is completed.
- The Museum received regulatory approval for the project after an extensive review process.Several City agencies, including NYC Parks and the Landmarks Preservation Commission, approved the project after a multi-year review process that included numerous opportunities for public comment.
- There is nothing out of the ordinary about the environmental conditions of Theodore Roosevelt Park. The results of the site investigations were typical of other construction sites in New York City. No evidence was found of an onsite chemical release, and the City’s expert agencies concluded that there are “no known risks with respect to hazardous materials that cannot be controlled through the use of the measures commonly used at construction sites throughout New York City.” This conclusion is corroborated by the fact that prior construction in the Park has never yielded any such concerns—including as recently as the Rose Center project. That project included work in parkland not previously occupied by the Hayden Planetarium and on the same site as the Gilder Center, for the reconfiguration of the Museum’s service yard, the construction of the Weston Pavilion, and improvements in the north and west parts of the Park.
In short, this is an important civic project that is in the public interest, which is why it has the support of public officials, without exception, and of Manhattan Community Board 7 and civic groups such as New Yorkers for Parks and Friends of Theodore Roosevelt Park.
I hope you find this update helpful. If you have any questions, please call 212-769-5246 or email [email protected].
Sincerely,
Michael J. Novacek, Ph.D.
Senior Vice President and Provost of Science
Curator and Professor of Paleontology
American Museum of Natural History
On Friday, November 2, the Museum won an important victory when an Appellate Court judge considerably limited the Temporary Restraining Order (TRO) imposed on the Gilder Center project, allowing work to proceed today, Monday, November 5.
David Paget (Sive, Paget & Riesel, P.C.), attorney for the American Museum of Natural History, issued the following statement on Friday, November 2:
“Today the American Museum of Natural History won a significant victory that will allow work to proceed immediately on the Gilder Center for Science, Education, and Innovation. Interior work and other necessary exterior work will begin Monday. For the time being, the Museum will not proceed with the removal of 7 trees pending determination of the overall merits of the case, on which we fully expect to prevail. We further expect the Gilder Center will move ahead as proposed, because both the authoritative legal precedent (from the highest court of New York State, as well as other court decisions) and the civic purposes of the project are clear. The City and the Museum have relied on and acted consistently in accordance with the more than 140-year-old New York State legislation, authorizing use of the Park for the Museum, and lease, and a full, transparent, and open engagement with the public, including hundreds of meetings, public hearings, and town halls. This project continues the Museum’s steadfast commitment to improve Theodore Roosevelt Park and the surrounding neighborhood, while also advancing its scientific and educational mission.”
For more information about the Gilder Center project, please visit the project website, amnh.org/gildercenter. For general inquiries, you can also call 212-769-5246 or email [email protected].
The 80th Street park path was completed and opened for use on September 25, and the installation of the construction site fence has begun. There are directional signs in the Park indicating park paths as well as signage informing Museum visitors to enter via the Rose Center for Earth and Space entrance on 81st Street.
The installation of the construction site fence is in progress and, as mentioned in the August 30 update, will be followed by the removal of the pedestrian islands at 79th Street and Columbus Avenue to allow for the creation of temporary protected bike and pedestrian paths in the curb lane. This work will begin as early as Thursday, October 4, and it will include the closure of the crosswalks at 79th Street. Pedestrians will still be able to use Columbus Avenue but will need to cross at 78th Street or 80th Street. The bicycle lane will remain open.
After the pedestrian islands are removed, the bike and pedestrian paths on the east side of Columbus Avenue will be shifted to run around the site fence. The pedestrian islands will be restored, and the 79th Street crosswalks will be reopened, once the Gilder Center is completed.
The Sunday 79th Street Greenmarket on Columbus Avenue will remain open, but beginning October 7 the farmers who usually set up north of 79th Street will move around the corner to 77th Street. The Museum is coordinating with NYC Department of Transportation, NYC Parks, and GrowNYC, which runs the greenmarket, on this transition. For more information, please check GrowNYC’s website.
For more information about the Gilder Center project, please visit the project website, amnh.org/gildercenter. For general inquiries, you can also call 212-769-5246 or email [email protected].
The fountains and lower portion of the Ross Terrace will reopen on Saturday, following the placement of trailers on the upper terrace. Visitors can access the Ross Terrace by using the staircase from Theodore Roosevelt Park or by entering the Rose Center at 81st Street and following signs to the second floor, where a new ADA-compliant entry leads to the Terrace from the Scales of the Universe walk.
Earlier this month the Museum's Columbus Avenue entrance (at 79th Street) was closed for interior demolition. There are directional signs in the Park informing visitors to enter the Museum from 81st Street.
There are ongoing preparations for the installation of the construction site fence. In the first two weeks of September, work is expected to begin on the temporary park access path near 80th Street. Tree protection will also be installed over the next several weeks, based on consultation with the New York City Parks Department. Once the path is installed and the tree protection is installed, the installation of the site fence will begin. Materials for this work, and for the site fence, will be delivered and staged in the park. With installation of the site fence, the pedestrian islands at 79th Street will be removed to allow for temporary protected pedestrian and bicycle paths around the site fence. This work is expected to take approximately 4-6 weeks following the installation of the temporary park path.
Tree removal and removal and storage of the landmarked stone piers at the West 79th Street entrance to the Park will begin after the site fence is installed. New trees will be planted and the piers will be reinstalled at the 79th Street entrance as part of the Park improvements the Museum will be making toward the end of the construction period.
For more information about the Gilder Center project, please visit the project website, amnh.org/gildercenter. For general inquiries, you can also call 212-769-5246 or email [email protected].
The lower terrace and fountains were closed August 6 and will remain closed for approximately three weeks to allow for the installation of trailers on the upper terrace. The trailers, which will temporarily house the Museum's Ichthyology Department, will be lifted by crane from the horseshoe driveway at the Museum's parking garage and onto the terrace (weather permitting). The crane will be onsite on August 16, with work going on overnight from approximately 6 pm until approximately 6 am on August 17. Because of its proximity to the crane, the Bull Moose Dog run will be closed while the crane operation is taking place (starting at approximately 8 pm) and will open at the regularly scheduled time (6 am) the next morning.
In mid-August the Museum will be closing the Weston Pavilion, our Columbus Avenue entrance, and beginning demolition inside that building.
The Museum will begin installing the site fence around the construction area in late August/early September. Before the site fence installation can begin, a temporary park path will be created at Columbus Avenue near 80th Street, to maintain continued access to Theodore Roosevelt Park and the Bull Moose Dog Run during construction. Pedestrian and bicycle circulation on Columbus Avenue will be maintained. The bike lane will be shifted west to accommodate the creation of a pedestrian walkway adjacent to the curb. Signs and barriers will be installed for the safety of the public passing through this area. The vehicular lanes of traffic will remain as they are.
In the next few weeks, arborists will be working with the NYC Parks Department to survey the park and to identify the trees that will require protection during construction. NYC Parks Department tree protection measures, including plywood enclosures as needed, will be placed around the protected trees. Other vegetation, fencing, and park furniture will be cleared from the construction area. Tree removal and removal and storage of the landmarked stone piers at the West 79th Street entrance to the Park will begin after the site fence is installed. New trees will be planted and the piers will be reinstalled at the 79th Street entrance as part of the Park improvements the Museum will be making toward the end of the construction period.
For more information about the Gilder Center project, please visit the project website, amnh.org/gildercenter. For general inquiries, you can also call 212-769-5246 or email [email protected].
Earlier this month, the Museum and Community Board 7 convened the first meeting of the Gilder Center Construction Task Force, which includes representatives from neighborhood groups. The Task Force will meet on a monthly basis to discuss construction-related issues. Zac Campbell remains the main contact for any Gilder Center construction-related questions or concerns from the neighborhood. You can reach him at 212-769-5243 or [email protected].
Thursday, July 19, after the Museum closes, Santiago Calatrava’s New York Times Capsule sculpture will be relocated. The plan to relocate the Times Capsule was approved by Community Board 7’s Parks and Environment committee in June, and by Community Board 7’s Full Board and the New York City Public Design Commission earlier this month. The Times Capsule, currently located in Theodore Roosevelt Park near Columbus Avenue and 79th Street, will be removed and temporarily stored before its reinstallation in its new location in the park along the 81st Street side of the Museum, near the entrance to the Rose Center for Earth and Space.
Over the past few months, three street trees and more than 90 shrubs have been relocated within Theodore Roosevelt Park. Arborists are currently implementing measures to help the trees recover from the transplant process and adjust to their new location.
The lower terrace and fountains, which reopened in June after a brief closure, are scheduled to be closed on or around August 6 for approximately three weeks to allow for the installation of trailers on the upper terrace. The trailers, which will temporarily house the Museum’s Ichthyology Department, will be lifted by crane from the horseshoe driveway at the Museum’s parking garage and onto the terrace. The crane will be onsite to lift the trailers within a single 48-hour time period during the terrace closure. All crane work will occur at night, and we will be sharing additional details as we get closer to the work.
Separately from the Gilder Center project, to accommodate work for another project, one of the windows of the Museum’s façade along Columbus Avenue near 78th Street (next to the Museum’s service drive) will be converted into a temporary passageway, and a second temporary passageway will be created at the northern end of that same building (facing north into Theodore Roosevelt Park).
For more information about the Gilder Center project, please visit the project website, amnh.org/gildercenter. For general inquiries, you can also call 212-769-5246 or email [email protected].
Following a short closure due to Gilder Center preparatory work, the lower portion of the Arthur Ross Terrace reopened this week, and the fountains are now on.
The upper terrace will remain closed for the duration of the Gilder Center project, and the lower terrace will close temporarily later this summer to allow for the placement of trailers on the upper terrace.
For more information about the Gilder Center project, please visit the project website, amnh.org/gildercenter. For general inquiries, you can also call 212-769-5246 or email [email protected].
Preparatory work for the Gilder Center project continues this month. Bartlett Tree Experts, advised by NYC Parks, will be relocating some of the shrubbery and plantings, as well as 3 street trees, to other locations within Theodore Roosevelt Park.
Preparatory work will also begin on the Ross Terrace. Prior to constructing the Gilder Center, some Museum functions will need to be relocated into temporary trailers that will be placed on a portion of the Terrace (the ‘upper terrace,’ where the tables and chairs are currently located).
To prepare this area, the Ross Terrace will be closed for approximately two to three weeks beginning June 4; the temporary trailers will not be placed until a later date. During this time, the pavers on the upper terrace will be removed and temporary fencing will be installed. This work will be done during the day and is not expected to be noisy. While the upper terrace will remain closed for the duration of the Gilder Center construction, the ‘lower terrace’ (the east-west path with benches) and fountains will reopen once this work on the upper terrace is completed.
For more information about the Gilder Center project, please visit the project website, amnh.org/gildercenter. For general inquiries, you can also call 212-769-5246 or email [email protected].
The New York City Department of Parks & Recreation (NYC Parks) and the Landmarks Preservation Committee (LPC) approved recent refinements to the design for the Richard Gilder Center for Science, Education, and Innovation, and preparatory work is underway on the 230,000-square-foot project, which will link advanced education and exhibition spaces with the Museum’s scientific facilities and collections.
Design refinements include an adjustment to the height of the parapet adjacent to the Museum’s southern-most building on Columbus Avenue, which will be 8 feet lower, for a more fluid connection at roof level; a connection between the two sides of the new Columbus Avenue entrance via an arching element; the separation of the roof skylight into a series of smaller skylights that allow for the roof on each side to be connected between the skylights and retain the sustainability benefits of a skylight system; and the reduction of bulk in the northeast side of the building, visible from the Ross Terrace, with the central window set back into the building. The unifying material for the northeast side of the building will be brick rather than copper. In addition, Studio Gang has made an interior enhancement to improve east-west circulation with a more centrally located staircase in the central exhibition hall, leading to a second-floor landing.
The NYC Parks approval letter is available for public review at http://nyc.gov/parks/amnh-gilder.
If you have any questions, please call 212-769-5246 or email [email protected].
Today the New York City Department of Parks & Recreation (NYC Parks) approved the Museum’s plans for the Richard Gilder Center for Science, Education, and Innovation, following completion of the environmental review process and issuance of its Statement of Findings. This approval allows the Museum to proceed with its plans to build the 245,000-square-foot project that will reveal current science to visitors of all ages through cutting-edge exhibitions and innovative educational programming.
The Statement of Findings and the approval letter are available for public review at http://nyc.gov/parks/amnh-gilder and at the following locations:
NYC Department of Parks and Recreation (NYC Parks)
The Arsenal in Central Park (contact Owen Wells, [email protected])
St. Agnes Library (444 Amsterdam Avenue)
If you have any questions, please call 212-769-5246 or email [email protected]
On November 15, New York City Department of Parks and Recreation (NYC Parks) issued the final Gilder Center Environmental Impact Statement (EIS). The EIS is available for public review at http://nyc.gov/parks/amnh-gilder and at the following locations:
NYC Department of Parks and Recreation (NYC Parks)
The Arsenal in Central Park (contact Owen Wells, [email protected])
St. Agnes Library (444 Amsterdam Avenue)
If you have any questions, please call 212-769-5246 or email [email protected]
On May 18, New York City Department of Parks and Recreation issued the draft Gilder Center Environmental Impact Statement (EIS). The draft EIS is available for public review at http://nyc.gov/parks/amnh-gilder or at the following locations:
NYC Department of Parks and Recreation (NYC Parks)
The Arsenal in Central Park (contact Owen Wells, below)
St. Agnes Library, 444 Amsterdam Avenue
NYC Parks will hold a public hearing on the draft EIS for the Gilder Center on Thursday, June 15, at 6:00 pm at the American Museum of Natural History. Enter at Weston Pavilion entrance, Columbus Avenue and West 79th Street, New York, NY 10024, and proceed to the LeFrak Theater.
Written comments will also be accepted by NYC Parks until 5:00 pm on June 26, 2017, addressed to the following address, fax number, or email address:
Contact person: Owen Wells, Director of Environmental Review
New York City Department of Parks and Recreation
The Arsenal, Central Park
830 Fifth Avenue, Room 401
New York, NY 10065
Telephone: 212-360-3492
Fax: 212-360-3453
Email: [email protected]
If you have any questions, please call 212-769-5246 or email [email protected]
On January 11, 2017, the Museum unveiled developing details about the new spaces, programs, and exhibits that will be housed in the proposed Richard Gilder Center for Science, Education, and Innovation. The project will house resources for education, exhibition, and research, and reveal modern science to visitors of all ages.
An Insectarium on the first floor will introduce visitors to some of the most abundant and diverse animals in the world through specimens from the Museum’s collections alongside live insects, scientific tools, and digital displays. And above the Insectarium, visitors will be able to encounter live butterflies from around the world in the Butterfly Vivarium, one of the Museum’s most popular seasonal exhibits, now a year-round living exhibition.
A multi-story, glass-walled Collections Core will house 3.9 million specimens and artifacts from the Museum’s incomparable collections, while the immersive Invisible Worlds Theater will help visitors visualize data and concepts that don’t lend themselves to traditional exhibition—nothing will be too fast, too slow, too small, or too deep in time to be explored in this new space.
In addition, the Gilder Center project will include next-generation classrooms for different age groups in dedicated learning zones. These will include classrooms in a Family Learning Zone, a Middle School Learning Zone that will invite in New York City schools without laboratory facilities to attend “research field trips," a High School Learning Zone, and a Teacher Professional Development Zone.
Designed by Studio Gang Architects under the leadership of Jeanne Gang and featuring exhibit design by Ralph Appelbaum Associates, the facility is expected to open in 2020, after the conclusion of the Museum’s 150th anniversary celebration.
“By showcasing the frontiers of research in ways that align with how people learn today, the Gilder Center will empower our visitors to directly engage with 21st-century science and with the larger world around them, while offering inspiring new spaces and opportunities for share learning, discovery, and community,” says Museum President Ellen V. Futter.
At a public hearing on October 11, 2016, the New York City Landmarks Preservation Commission (LPC) unanimously approved the Gilder Center application, commending the proposed design as a "stunning piece of architecture."
AMNH_Landmarks Preservation_Commission_Application_09082016
"It's going to be a wonderful addition to one of the best institutions in the world," said LPC Chair Meenakshi Srinivasan.
"The Gilder Center for Science, Education, and Innovation is designed to enhance the public understanding of science by letting all visitors share in the excitement of discovery," said Museum President Ellen V. Futter.
"The Museum has been working with the architect to make sure the project respects the existing Museum campus and its location in a landmark district and in a public park. Today's hearing is an important step in the approvals process, and we appreciate the careful consideration of the Landmarks Preservation Commission."
Manhattan Community Board 7 voted on Wednesday, October 5, 2016, by an overwhelming majority to approve the architectural design for the American Museum of Natural History's proposed Gilder Center for Science, Education, and Innovation and the landscape design for a section of the adjacent Theodore Roosevelt Park, located east of Columbus Avenue between 79th and 81st Streets.
Before the two separate resolutions were presented for a vote by the full Community Board, they were discussed and approved on a near-unanimous basis on September 20 at a joint meeting of the Board's Preservation and Park and Environment Committees. Community Board 7's deliberations are part of the process for seeking approval for the designs from the Landmarks Preservation Commission.
The architectural design for the proposed building is by Jeanne Gang, principal and founder of Studio Gang Architects. The renovated landscape design for Theodore Roosevelt Park is by Reed Hilderbrand.
"The Museum is deeply grateful for the careful and extensive review that Community Board 7 has given our proposal," said Museum President Ellen V. Futter. "Community input has played an important role in this project, and we are delighted that the Community Board, along with numerous neighborhood organizations, has offered this strong endorsement."
Among the groups that support of the project – some of whose members spoke at the Board meeting—are Friends of Roosevelt Park, Park West 77th street, Columbus Avenue Business Improvement District, Theodore Roosevelt Park Neighborhood Association, West 80th Street Block Association, American Institute of Architects (AIA) New York Chapter, New Yorkers for Parks, and Green Market/Grow NYC.
2016
AMNH: Public Information Session re: Landmarks Application
Sep. 13, 2016
CB7: Joint Preservation/Parks Committee Meeting
Sep. 20, 2016
CB7: Vote on Landmarks Application
Oct. 5, 2016
LPC: Public Hearing on Landmarks Application
Oct. 11, 2016
2017 [dates to be determined]
CB7: Public Hearing on Draft Environmental Impact Statement
PARKS: Public Hearing on Draft Environmental Impact Statement
After consultation with the NYC Department of Parks & Recreation (NYC Parks), the American Museum of Natural History and Park Working Group today announce that as part of ongoing planning and design for the Richard Gilder Center for Science, Education, and Innovation, the Museum is developing plans to protect and conserve two notable trees, an English elm and a Pin oak, located in Theodore Roosevelt Park, near the Museum's Columbus Avenue entrance at 79th Street. Conserving these two trees reduces the number of trees removed due to construction from nine to seven.
The conclusion that it is possible to preserve the two trees is based on the results of two analyses: a general engineering study of the proposed service drive that shows, among other things, that the drive could be designed to serve its essential function without requiring the removal of the English elm and the Pin oak; and an assessment from Bartlett Tree Experts of the feasibility of protecting the long-term health and survival of the trees—during and after construction—and their recommendations for doing so. Based upon this information, the Museum is developing a design for the Gilder Center and surrounding parkland that conserves and incorporates the two trees.
"Saving these trees is the most recent demonstration of the Museum's efforts to be a thoughtful community partner. I am thrilled that these two important trees will remain and that the Museum continues to take steps to do all it can to address community issues while maintaining the important mission of this Center," said Helen Rosenthal, New York City Council Member, District 6, Upper West Side of Manhattan.
In developing their recommendations, Bartlett Tree Experts considered a range of factors including the overall health of the trees, their ability to withstand severe storms, and the likelihood that they would survive the construction process in good condition. Plans call for the Museum to plant more trees after construction than were removed during the project. The exact number will be determined as part of the park design process.
The Park Working Group is co-chaired by the Museum and Friends of Roosevelt Park, and its members include representatives from the offices of: Manhattan Borough President Gale Brewer, New York City Council Member Helen Rosenthal, Assembly Member Linda Rosenthal, the New York City Department of Parks & Recreation, Manhattan Community Board 7, the West 77th Street Block Association, Theodore Roosevelt Park Neighborhood Association, the Defenders of Teddy Roosevelt Park, and the Columbus Avenue Business Improvement District.
The New York City Department of Parks and Recreation, as lead agency, will conduct a City Environmental Quality Review (CEQR) public scoping meeting at the Museum on April 6, 2016.
The Draft Scope of Work for the Gilder Center EIS is available for public review at http://nyc.gov/parks/amnh-gilder or at the following locations:
NYC Department of Parks and Recreation
The Arsenal in Central Park (contact Owen Wells, below)
St. Agnes Library, 444 Amsterdam Avenue.
DPR will hold the Public Scoping Meeting on Wednesday, April 6, 2016 at 6:30 p.m. at the American Museum of Natural History, LeFrak Theater. Enter at Weston Pavilion entrance, Columbus Avenue and West 79th Street, New York, New York 10024.
Written comments will also be accepted by DPR until 5 pm on Wednesday, April 20, 2016, addressed to the following address, fax number, or email address:
Contact person: Owen Wells, Director of Environmental Review
New York City Department of Parks and Recreation
The Arsenal, Central Park
830 Fifth Avenue, Room 401
New York, New York 10065
Telephone: 212-360-3492
Fax: 212-360-3453
Email: [email protected]
Please join us at the Museum for an informational meeting about the Richard Gilder Center for Science, Education, and Innovation on Thursday, November 12 from 6:30 to 8:30 pm.
The meeting will feature a presentation by architect Jeanne Gang on the recently announced conceptual design.
Please enter at 77th Street between Central Park West and Columbus Avenue.
RSVP by calling 212-769-5246 or by email to [email protected].
Download the meeting flyer here:
The Board of Trustees of the American Museum of Natural History today endorsed the conceptual design for the Richard Gilder Center for Science, Education, and Innovation, a new building that will invite visitors to experience the Museum not only as a place of public exhibitions but as an active scientific and educational institution. In addition, the Board authorized proceeding to schematic design.
Designed by architect Jeanne Gang of Studio Gang Architects and set into the Columbus Avenue side of the Museum complex at 79th Street, the Gilder Center is the embodiment of the Museum's increasingly integrated mission of science, education, and exhibition. At a time of urgent need for better public understanding of science and for greater access to science education, the Gilder Center will offer visitors, including the general public and school groups, new ways to learn about science and to share in the excitement of discovery. To ensure that the next generation has the skills and imagination for scientific innovation, the Gilder Center will provide interdisciplinary learning spaces that place STEM (science, technology, engineering, and math) and other educational experiences in the context of world-class scientific research and collections.
The conceptual design for the Gilder Center is consistent with longstanding but previously unrealized aspects of the Museum's 1872 master plan, while reflecting a contemporary architectural approach that is responsive to the Museum's mission and to the current uses and character of the surrounding Theodore Roosevelt Park and neighborhood.
"The Gilder Center embraces the Museum's integrated mission and growing role in scientific research and education and its enhanced capacity to make its extensive resources even more fully accessible to the public," said Museum President Ellen V. Futter. "It will connect scientific facilities and collections to innovative exhibition and learning spaces featuring the latest digital and technological tools. Jeanne Gang's thrilling design facilitates a new kind of fluid, cross-disciplinary journey through the natural world while respecting the Museum's park setting."
Architectural Concept
In developing the architectural concept for the new Center, Jeanne Gang worked from the inside out. She saw an opportunity to reclaim the physical heart of the Museum and to complete connections between and among existing Museum galleries and new space, leading to a conceptual design that includes links to 10 Museum buildings through 30 connections. "We uncovered a way to vastly improve visitor circulation and Museum functionality, while tapping into the desire for exploration and discovery that are emblematic of science and also part of being human," said Gang. "Upon entering the space, natural daylight from above and sightlines to various activities inside invite movement through the Central Exhibition Hall on a journey towards deeper understanding. The architectural design grew out of the Museum's mission."
In designing the Central Exhibition Hall, which will serve as the Museum's Columbus Avenue entrance, Gang came up with the core idea of connecting this space to the geographic center of the Museum. Informed by processes found in nature, the gallery forms a continuous, flowing spatial experience along an east-west axis, allowing visitors to move beneath and across connective bridges and along sculpted walls that house the Museum's many programs. Recessed cavities in the sculptural walls create niches that will house exhibition elements designed by Ralph Appelbaum Associates, as well as laboratories, imaging facilities, visualization theaters, and classrooms while also revealing more of the Museum's extensive scientific collections. Following Studio Gang's signature approach, in which material and structure are expressed for their inherent properties, the reinforced concrete walls of the Central Exhibition Hall, with its arches and niches, will have more than a purely aesthetic purpose: they will form the weight-bearing structure of the building's interior.
The visual language of the Central Exhibition Hall informed the conceptual design of the façade, which imagines the interior walls emerging and wrapping around the exterior. The exterior will be clad in glass and stone, which will be selected in the upcoming design phase with consideration of materials used in the existing complex. The conceptual design maintains the current heights of the Museum building complex on its western side, placing the Columbus Avenue façade at the same height as the buildings on either side of the new entrance. On the south side, the façade is aligned with the adjacent building and steps back to meet the bordering building to the north. The conceptual design is consistent with the axial intention of the original 1872 master plan while recognizing the park setting in which the Museum is located.
The design greatly enhances visitor circulation at a museum where annual attendance has grown from approximately 3 to 5 million over the past several decades. It connects an array of existing galleries to new ones in ways that highlight intellectual links across different scientific disciplines, create adjacencies among and facilitate interaction within classrooms, laboratories, collections, and library resources, and place educational experiences within current scientific practice.
"With active learning environments for classes and the general public that better align with the highly interdisciplinary world that we live in, the Gilder Center will reveal the latest scientific thinking and its relevance to many of the most important issues of our time. It will enable learners of all ages and backgrounds to better understand the world around them and their place in it. It will also connect for the first time, both physically and intellectually, many of the Museum's existing galleries, thereby vastly improving visitor circulation and experience," said Futter.
"We are focused on the needs of 21st-century learners, offering unparalleled opportunities to engage with science and scientists. The exhibits in the Gilder Center will incorporate a blend of innovative learning strategies and imaging technologies with the Museum's extraordinary collections and far- reaching scientific research," said Ralph Appelbaum of Ralph Appelbaum Associates. Mobile technology will be integrated throughout the new Center for seamless links between onsite and digital visitor journeys of discovery, a fully realized extension of what the Museum first piloted in 2010 with the introduction of the first indoor-navigation app, Explorer, which is currently being updated with more personalized and contextualized features.
Science and Education at the Museum
Since its founding in 1869, the Museum has had a dual mission of science and education. Over the last two decades, these two aspects of the mission have become increasingly integrated. The Museum has established the Richard Gilder Graduate School, which grants both the Ph.D. degree and the degree in Master of Arts in Teaching with a specialization in Earth science. It works with partners on the national, state, and local levels to pilot and develop innovative programs that leverage its unique scientific resources to help address challenges in STEM education, substantially extending its role in enriching formal science education and in providing professional development for teachers. The Museum's robust and growing portfolio of educational programs includes partnerships with schools, teacher professional development programs, and out-of-school programs for students that offer authentic research experiences, introduce digital tools of science, and explore college and career opportunities.
Major initiatives include the Urban Advantage Program, spearheaded by the Museum in partnership with seven other cultural institutions, the New York City Department of Education, and the Council of the City of New York, which this year will serve about 800 teachers in about 45 percent of the City's middle schools across all five boroughs and which reaches approximately 80,000 students; onsite professional development offerings for roughly 4,500 teachers, ranging from intensive workshops to introductions to the Museum and learning resources for their students; and out-of-school programs for students from pre-K through high school that serve approximately 2,500 participants a year. The demand for these educational offerings, as well as participation, has grown across the board, but the space dedicated to education classrooms is insufficient, out of date, fragmented, and difficult to access. By both adding and updating learning spaces, the Gilder Center will significantly enhance the Museum's capacity to serve New York students, teachers, and families.
"The American Museum of Natural History is so many things to New York: a cutting-edge research institution, an educational powerhouse, and a resource that New Yorkers and their families have enjoyed for generations," said acting Cultural Affairs Commissioner Edwin Torres. "We look forward to working with the Museum to create an asset that allows residents and visitors even greater access to its extraordinary programming and exhibitions."
Exhibition and Program Elements
More than any other gallery, the Central Exhibition Hall and the niches housed in its walls will reveal the Museum as an active scientific and educational institution with closely integrated educational experiences, scientific resources, and exhibition areas. The public will be able to engage with innovative tools used by Museum scientists, such as the tools used for gene mapping, 3D imaging, and big data assimilation and visualization, to gain a deeper understanding of nature's complexity and how science is conducted today.
The Central Exhibition Hall will include a variety of education areas for learners of all ages and levels, including approximately the 500,000 visitors who come to the Museum as part of school and camp groups each year. Students of all backgrounds will have opportunities to observe and participate in the processes of scientific discovery in spaces designed to facilitate cross-disciplinary thinking and personalized learning.
"A distinctive strength of the Museum's educational programs is that they offer a connection to actual scientific work, practitioners, and the tools and methods of scientific thinking and research. The Gilder Center will extend this experience to all visitors, providing a way for all to ask questions and to connect the dots between scientific discoveries and our daily lives," said Futter.
Closely integrated exhibition and program elements in development include:
- The Collections Core, a vertical feature spanning several floors that will showcase a working section of the Museum's world-class collections and the activities of researchers who come to study its invaluable specimens and artifacts, which together form an irreplaceable record of life on Earth.
- The Invisible Worlds Theater, an immersive theater that will reveal new frontiers of scientific research made accessible with new imaging technology, from the intricate architecture of the human brain to our microbial ecosystem, and from the shadowy depths of the ocean to the outer reaches of the atmosphere.
- The Museum Library—one of the largest and most important natural history libraries in the world, which will now be revealed and made accessible to visitors and will offer a space for reading and contemplation surrounded by spectacular views of the Central Exhibition Hall and Theodore Roosevelt Park.
- An insect hall, which will showcase the variety of one of Earth's most diverse and abundant groups with specimens from the Museum's insect collection, one of the world's largest and most diverse collections of its kind, and live insects. The hall also will be the new home of the Museum's popular live butterfly conservatory.
- An interpretive wall, located at the center of the Museum's building complex, which will orient visitors, facilitate way-finding, and spark further exploration by showcasing current science, illuminating important concepts such as geologic time scales and evolutionary relationships, and issuing real-time updates on the pulse of our planet in a mosaic of video, data imagery, and interactive exhibits. The interpretive wall will not only anchor the onsite visit but will also become a crucial part of a seamless visitor journey that integrates onsite experiences with visitors' digital interactions with the Museum.
- Exhibition niches, a series of open, recessed chambers with exhibitions that will connect the wonders of the natural world with our own powers of perception and sensation. Visitors will experience such phenomena as the deep blue light emitted from the depths of an ice cave, the sounds of a tropical rain forest teeming with life, and the ultrasound cries of bats in the night sky and of whales in the deep ocean—sounds that are out of range to the human ear without the aid of sensitive sonars.
- Educational laboratories and classrooms, which will directly address the need to enhance STEM teaching and learning and enable teachers and students to access the Museum's extensive scientific resources. New facilities in the Gilder Center will allow students to carry out research projects in data visualization and assembly that mirror those conducted by Museum scientists and better prepare them for secondary education and the workforce. Classrooms featuring the latest digital and technological tools will be connected to scientific facilities and collections, and will offer innovative spaces for teaching science to middle school, early childhood, family, and adult learners.
- Scientific laboratories, which will be equipped with powerful state-of-the-art optical and electron microscopes, CT scanners, and workstations for 3D reconstruction and animation, will enable Museum scientists to image and analyze extensive amounts of information resident in fossil organisms, meteorites, and even cultural objects—all at levels of detail and accuracy that far exceed anything thought possible even a few years ago. Adjacent spaces will be devoted to investigators conducting computational research on big data produced through these detailed visualizations, with visitors having opportunities to observe ongoing lab investigations and resulting visualizations.
Project Information
The Gilder Center is named for Museum Trustee Richard Gilder, who has donated more than $125 million to the Museum, including $50 million for the new center. The project cost is estimated to be $340 million, of which more than half has been raised.
Approximately 80 percent of the 218,000-square-foot project will be located within the area currently occupied by the Museum, creating vital connections throughout the complex. Three existing buildings within the Museum complex will be removed to minimize the impact on land that is now open space in Theodore Roosevelt Park to about 11,600 square feet (approximately a quarter acre).
If approved, construction of the Gilder Center will begin in 2017 after completion of the design. The goal is to open the Gilder Center in 2020, at the conclusion of the Museum's 150th anniversary in 2019.
Project Team
In addition to Studio Gang Architects and Ralph Appelbaum Associates, the Museum has engaged landscape design firm Reed Hilderbrand to work with the Parks Department on a proposed design for the part of the Theodore Roosevelt Park that borders the new Gilder Center.
The project management team on the project is Zubatkin Owner Representation.
Museum Architectural History
The history of the Museum's architecture has always been an interplay between the original master plan, the evolution of architectural styles, and the institution's changing functional, scientific, educational, and technological needs. The original master plan, which envisioned a great square with rigorous symmetry in the four street façades, was realized in the south façade but only partially completed in the north, east, and west sides of the Museum complex.
The Gilder Center conceptual design is consistent with the master plan while continuing the Museum's long history of expressing its institutional identity, and the science of the day, in an architectural language that is fitting to its time and place, including its location in the Park.
The Board of Trustees of the American Museum of Natural History has voted to authorize the creation of a new Center for Science, Education, and Innovation, the selection of Studio Gang Architects, led by MacArthur Fellow Jeanne Gang, to design it, and the selection of Ralph Appelbaum of Ralph Appelbaum Associates to design the exhibitions. Museum Trustee Richard Gilder has made the lead gift, and the new Center will be named in recognition of his lifetime of extraordinarily generous giving which, inclusive of a new $50 million gift, totals over $125 million and makes him the single largest donor in the Museum's history.
"Science, education, technology, and innovation are driving forces of our time," said Ellen V. Futter, President of the American Museum of Natural History. "From human health to the environment, many of the most important issues facing our society embody science, and it is essential that the public understanding of these vital topics be enhanced. At the same time, the role of museums is changing and the American Museum of Natural History aims to have a growing impact on science literacy and STEM education. Thanks to Dick Gilder's extraordinary generosity, the new Gilder Center for Science, Education, and Innovation will enable a wholly new type of museum experience, and we are extremely grateful to him for his leadership and vision."
"Over the last two decades, the American Museum of Natural History has been transformed, and Dick Gilder has been there at every major turning point, from the creation of the Rose Center for Earth and Space to the establishment of the Richard Gilder Graduate School," said Lewis W. Bernard, Chairman of the Board of Trustees. "Where everyone else sees merely an unmet need, Dick sees opportunity. His latest exceptional gift will solidify his place as one of the most important figures in the Museum's history."
The new project, comprising approximately 218,000 square feet of existing and new space, is estimated to cost approximately $340 million, of which more than $100 million has been raised. The Museum's goal is to open the new Gilder Center, which will be located on Columbus Avenue at 79th Street on the west side of the Museum campus, in conjunction with its 150th anniversary in 2019–2020. In accordance with the Board of Trustees vote, the Museum will now begin the process of design and community consultation.
The new Center will reflect the full range of the Museum's integrated mission of science and education, letting visitors share in the excitement of scientific discovery, and will be the first project of this scope since the mobile revolution. The Gilder Center will significantly enhance the Museum's already-strong capacity to serve New York City school children, teachers, and families with such planned facilities as a new family learning center and a middle school academy. The new Center will also include exhibition galleries designed to reveal the mysteries of the natural world through current tools of scientific observation and innovative onsite and digital experiences. A new presentation venue will explore today's thrilling scientific investigation of unseen worlds inside the human body and brain, at the frontier of the ocean depths, and the outer reaches of the atmosphere. The Center also will provide additional portals for the public to explore the Museum's research collection of more than 33 million objects and specimens and to connect with the ongoing work of Museum scientists in state-of-the-art laboratories for research, imaging, and visualization.
Extension of scientific and educational mission
The need for the new Gilder Center results in large measure from the dramatic extension of the Museum's scientific research initiatives and education programs over the last two decades, a time in which the Museum's annual attendance has also increased from approximately 3 million to approximately 5 million. The opportunity to provide a venue where, utilizing cutting-edge scientific tools and exhibition techniques, visitors can engage in the most crucial scientific questions of our time—human biology and health, the environment, mass extinction, and evolution—comes just as the Museum's scientific scope has grown. Today, it includes the sequencing of whole genomes; the use of CT scans, 3D computer animation, and other visualization technologies; and the application of ultra-high-speed computing for complex problems that range from evolutionary relationships among species, the origin of languages in diverse cultures, and the spread of infectious diseases.
The transformation of the Museum's educational enterprise has been particularly significant. Over the past two decades, the Museum has greatly expanded the scope of its educational offerings, including the number of students (approximately 500,000 school-aged children visiting in school and camp groups) and teachers (approximately 5,300 in professional development and teacher education programs) it serves annually, and the ways in which it does so. In 2003, the Museum led seven other New York City science institutions in the creation of Urban Advantage, a comprehensive science-learning approach for students and teachers, which now serves a third of all City middle schools across the five boroughs.
In 2008, the Museum, which became one of only two museums in the world authorized to grant the Ph.D., admitted the inaugural class to its Richard Gilder Graduate School. In 2011, the Museum became the first to offer a free-standing Master of Arts in teaching Earth science. The Museum has long been a destination for school field trips and family visits, but today it works in partnership with Education Departments at the Federal, State, and City levels to formally connect Museum resources to teacher education and professional development and to school curricula. In addition to teacher-focused programs, the Museum is home to dozens of educational programs, including those that provide training in and mentoring for middle school, high school, and college students in conducting authentic scientific research.
Architectural and exhibition design selection
After reviewing proposals from a number of architects, the Museum selected Studio Gang Architects, led by MacArthur Fellow Jeanne Gang, to design the Gilder Center. "It was apparent that Jeanne Gang embraced the Museum's legacy in science and education, and she has demonstrated a pervasive sensitivity to sustainability and the relationship between nature and the built environment, particularly in urban settings," said Ms. Futter. "Jeanne's approach could not be more appropriate, since introducing New Yorkers and visitors from around the world to science and the natural world is what the Museum has done since its founding in 1869. Throughout her career, Jeanne has shown a special passion for projects that combine innovative, mission-driven design, with a commitment to creating community spaces that facilitate onsite and digital access."
"I was immediately struck by the immense range of work the Museum is already doing as an educational facility to reach learners of all ages," said Jeanne Gang, founder and design principal of Studio Gang. "This project and collaboration with the Museum is incredibly important to me and my entire team. The Gilder Center's holistic mission closely aligns with Studio Gang's interdisciplinary practice of integrating architecture, nature, science, and art. Designing spaces that facilitate interaction between science, education, and exhibition experiences will make possible the learning the new Gilder Center aspires to generate."
Ralph Appelbaum of Ralph Appelbaum Associates, who previously designed the exhibits in the Museum's Rose Center for Earth and Space, the fourth-floor fossil halls, and the Hall of Biodiversity, has been chosen to design the exhibition experiences for the Gilder Center.
"The Gilder Center connects the latest in innovative learning strategies and imaging technologies to the Museum's extraordinary collections and far-reaching scientific research," explained Appelbaum. "Focusing on the needs of 21st-century learners, it will offer unparalleled opportunities for hands-on engagement with science and scientists in a seamless blend of great architecture and amazing evidence of what we know and what Museum scientists are uncovering in almost daily new discoveries. The new tools we have to make the invisible visible, understandable, and relevant will continue the Museum's trail-blazing role as a global leader in free-choice learning and informal education. This will be the place where young people especially will discover their passion for science, engage with new communities through integrated social media, and find their futures—it's a vision of the Museum of the 21st century made real."
Evolution of the Museum Campus
In 2000, the opening of the Rose Center for Earth and Space made possible a complete modernization of the Museum's planetarium, including its presentation of the science of astrophysics and Earth science. In 2009, the Museum completed a restoration of the historic 77th Street façade, one of the first structures built specifically to house American Museum of Natural History collections and galleries. And in 2012, the Museum completed the restoration of the 1936 Theodore Roosevelt Memorial, which includes its Central Park West façade and honors America's "Conservation President" and the commitment to environmental conservation that he advanced. In considering this new Center, the Museum is not only seeking additional space for critical public education, exhibition, and scientific purposes but is also planning to create an entrance on Columbus Avenue at 79th Street.